Location : Horana , Sri Lanka |
|
| |
Client : Arpico Plastics Ltd |
|
| |
|
|
| |
Requirements : Designing and building of 2 pre-engineered Steel Building, 40000 & 20000 Sq ft. |
|
| |
|
|
| |
Challenges : Construction of all works from Foundation level. Given the variety of businesses the factories will house it is critical to complete all works during very short period of time. |
|
| |
|
|
| |
Schedule : Planning, Analysis & Design Contract commenced in March 2007 and was completed in May 2007. Construction commenced in June 2007 and estimated to be completed by November 2007. |
|
| |
|
|