Location : Negambo, Sri Lanka.
|
|
| |
Client : R.P.C. Retail Development (Pvt) Ltd.
|
|
| |
|
|
| |
Requirements : Stage 1: Site preparation work for the construction of a Super Center Complex. Land Extent 1.37 acres. - Completed.
Stage 2: Construction of the Foundation and Super Structure of the Super Center Complex.
|
|
| |
|
|
| |
Challenges : This is a Concrete Structure with a floor area of approximately 56,000 Sq ft. Completion of the Civil and M & E Works within a short period of 5 month will be a challenge. Night work is being planned for timely completion. |
|
| |
|
|
| |
Schedule : Foundation work commenced in July 2007. Targeted date of completion is November 2007. |
|
| |
|
|